Monthly Update - October 2022

Current Month report

Continuing to actively turning up customers.

- Stoney Fork Road - continued

- Lipscomb Road - Continued

Main Line Construction continues.

- Stewartville Road Primary Main Line – (from SRHS to Jordontown Road) – Aerial plant – delayed due to AEP permit waiting approvals

Construction continues at the EastLake Church Neighborhood

- Hendrick Store Road - (mainline – buried construction continues)

- Timberwood Lane - (mainline – buried construction continues)

- Crystal Shores Drive - (mainline – buried construction continues)

- Wayfarer Lane - (mainline – buried construction continues)

- Custers Cove Way - (mainline – buried construction continues)

- Brook Run - (in construction schedule - continues)

- White Cap Lane - (in construction schedule - continues)

- Aspen Road - (in construction schedule - continues)

- Red Oak Rd - (in construction schedule - continues)

- Peninsula Drive - (in construction schedule - continues)

- E Road, D Road, B Road - (after further survey - changed to drops only for this campground)

- Bent Tree Road - (in construction schedule - continues)

- Oak Hollow Road - (in construction schedule - continues)

- Pine Knob Circle - (in construction schedule - continues)

- Meadow Point Drive - (in construction schedule - continues)

Huddleston Expanded Footprint

Permits pending submission or pending approval with VDOT

- Smith Mountain Parkway (Still awaiting VDOT approval, Permitting Requirement changed and they want them resubmitted)

- Dundee Road (Still awaiting VDOT approval, Permitting Requirement changed and they want them resubmitted)

- Altice Road (Still awaiting VDOT approval, Permitting Requirement changed and they want them resubmitted)

- Bold Branch (Still awaiting VDOT approval, Permitting Requirement changed and they want them resubmitted)

- Patmos Church Road (Still awaiting VDOT approval, Permitting Requirement changed and they want them resubmitted)

- Feldspar (Still awaiting VDOT approval, Permitting Requirement changed and they want them resubmitted)

Expanded Moneta Foot Print

Permits pending submission or pending approval with VDOT

- Construction scheduled to begin on Moneta Road (from Food Lion to the Bridge) – (Still awaiting VDOT approval, Permitting Requirement changed and they want them resubmitted)

- Dickerson Mill Road - (Still awaiting VDOT approval, Permitting Requirement changed and they want them resubmitted)

- Emmaus Church - (Still awaiting VDOT approval, Permitting Requirement changed and they want them resubmitted)

- Diamond Hill Road - (Still awaiting VDOT approval, Permitting Requirement changed and they want them resubmitted)

- Goodview Road (Diamond Hill Side) - (Still awaiting VDOT approval, Permitting Requirement changed and they want them resubmitted)

- Trading Post Road - (Still awaiting VDOT approval, Permitting Requirement changed and they want them resubmitted)